Reading RPLS is free for the whole profession. Members post, reply, and get the members-only rooms.
In Carlson, when creating points, in a subdivision, it labels all the Radius Points RADPT.
That clutters up my worksheet.
It should say RP. That's all we ever used on lath, when doing const staking. Real Estate space on a lath is at a premium.
In TDS Ranger, it calls intersections "INTERSECTION". Why? Why not just int? NONE of these codes should be more than 2 characters.
Also, why don't we allow up to 250 characters of note, in data collectors? Or 500 characters?
All that needs displayed is the 1st 20 characters, or so. That number should be SELECTABLE so that we can show only the 1st 10 if we like. Or the 1st 25 if we like.
Stuff like this is called feedback, from the dirty world where the equipment actually gets used.
In Carlson, we should be able to hover over a point, and a little box pops up with the WHOLE point description.
From my field book, this is a typical note:
S 40d 2" dp, ctrl pt. 9' NE to PPole. 18' N to F, 5' E to F. 14.5 SW to Ep.
Or:
Fd 40d Spike nail in RK Pile, 0.8' N & 1.2' E to FC - F runs N-S-W Set 1/2" rebar w cap, up 4".
Fd 1/2" pinch top pipe, nearly rusted out and gone. Pulled, and checked. Reset 3/8" rebar inside, to preserve position. 14' N to Fnc.
Electronic Field Books don't work for Rural Land Surveying, where CODES don't have alot of bearing on all the stuff we find.
Fd Octagonal Gun Barrel, 1' S & .5 W to round Cedar FC, N-S-W. Witness: 335d 14.85' 21" SG, w/ alum na on rt side-- 92d 7.41 6" elm, w Y blaze, and alum na on lt side. and old Location Poster, marked with pencil, rusted, Says CJ Co Surveyor, 1971,
This is typical. Why don't our data collectors address what surveyors actually do?
Do you want more in this area?
Thanks
Nate
Klutzy stuff in standards
Ever work with the NCS layers? We are trying to work towards those for sub work for a BIG engineering firm. Their CAD guys said NCS would be great, but they are missing some layers and have too many others for my liking. Plus the #-####-####-####-#### is annoying. Plus the organization is not smart. Nothing is in order, things don't make sense.
Klutzy stuff in standards
> Ever work with the NCS layers? We are trying to work towards those for sub work for a BIG engineering firm. Their CAD guys said NCS would be great, but they are missing some layers and have too many others for my liking. Plus the #-####-####-####-#### is annoying. Plus the organization is not smart. Nothing is in order, things don't make sense.
I only understood the words you wrote. But none of the ideas, or concepts.
I don't know what NCS layers are, and I don't know what the #### stuff is.
At least, I don't think I do.
Whatchewtalkinboutwillis?
N
Klutzy stuff in standards
> Ever work with the NCS layers?
They may be annoying, but at least they're "standard"
Just checked...I have 96 different C3D templates and 10 different MicroStation workspaces available on my network.
My guys are out running control on a new project this week that has to be delivered in Smithsonian Institution CAD standards. Really, a freaking museum has their own CAD standards. Oh, they work in metric too.
Once you have made your computations and are satisfied with them you can download your points file and run it thru a text editor and change them to something else (INTERSECTION to X) using the find and replace function to change them.
I do that to change descriptions when my helper has used some oddball note.
😉
Thanks. It's just annoying.
N
Klutzy stuff in standards
I did not see where surveyors helped create the standard and we do not get a discount for the package.
They may be standard, but they are missing a few items I would deem KEY.
Klutzy stuff in standards
There is at least one licensed surveyor on the Project Committee that I know of.
There also are vacancies on the Survey/Civil Task Team. The application to volunteer can be found here 😉
Klutzy stuff in standards
Thanks. Ye olde Cad cadres, are makin me life rumble.... CAD standards would have a problem with what I normally place in me field books. Engineers. Yup. Some injuneers need to be whipped!
Frankly, that is what the field book is for, diagrams and notes to insure correct interpretation of the work flow in the data collector.
Stuff in standards
:good:
[sarcasm]My standard is not the best but it is better than the NCS standard.[/sarcasm]
Stuff in standards
Stick it to the man.
Power to the people.
Klutzy stuff in standards
The NCS wants money, this link is to a very similar , and free, version of the same from the US Corps of Engineers.
The standard allows for the user creating new layers, you just have to follow the format.
Radius Point staking
> In Carlson, when creating points, in a subdivision, it labels all the Radius Points RADPT.
> That clutters up my worksheet.
Aloha, Nate:
This is kind of hijacking your post...sorry.
I am just curious about Radius point staking and have couple questions.
1. A curve could have a radius of 400 ft. and that point could fall somewhere on the site that is not easily accessible. What is the common practice when this happens?
2. What would be elevation assigned to the Radius Point? Same as PC or PT's know elevation or left zero?
Thanks
Radius Point staking
> 1. A curve could have a radius of 400 ft. and that point could fall somewhere on the site that is not easily accessible. What is the common practice when this happens?
Offset points (from the curve, not the radius)
> 2. What would be elevation assigned to the Radius Point? Same as PC or PT's know elevation or left zero?
Dependent upon your preference and the contractors needs.
Radius Point staking
Thanks Kevin! Aloha
Radius Point staking
It all depends on what you are trying to accomplish. Most of mine are roads, that intersect property lines. The elev does not matter. But, when doing const staking, it really matters. But, the RP elev... I don't think it matters much. Lots of things go on, along the alignment of the road, that does not affect the RP. Way back when I did const staking, we set a theodolite at the PC or PT, sited the PC or PT or the back TAN, and ran the curves in, in segments, using 3 man crew. 2 were taping. Then, we added elev to the hubs, for cut and fill. This was done in 2 steps. Set the hubs correctly for horiz, then add elev with a level. This was common procedure.
N
Radius Point staking
Aloha, Nate:
Thanks for more details for these questions. Enjoy your weekend!
Klutzy stuff in standards
"The nice thing about standards is you have so many to choose from."