RE: WGS84...Again

This is why Substantial control points should be set on the job siteso if the control points shift over years due to continental drift the control poi...

9 years ago
Reply
RE: GPS to TS

Just live with it = its there no big deal like there is going to be a difference between a good edm and a less accurate edm never loose any sleep.if t...

9 years ago
Reply
RE: GPS under transmission lines

I worked right next to the largest 500 KV switch yard in BC for 4 months with the base about 200 meters away from HV lines / massive transformersthe r...

9 years ago
Reply
RE: GPS under transmission lines

Zero Problems next to 500KV substation and towers for 6 monthsMulti path for GPS electronics from the books i have read is most difficult for the hard...

9 years ago
Reply
RE: 3 Leica GS 14 new 2017 January 2 Carlson DCs

Hi Nate And LeeWell the GS 14 and Trimble are under a 1.0 kG I have a trophy for Javad and TopconJavad 3.75 lbs (1.7 kg)/4.02 lbs (1.82 kg) with modem...

9 years ago
Forum
Topic
Forum
Replies: 4
Views: 958
Reply
RE: The fence builders cometh

Bill93, post: 446127, member: 87 wrote: It would make more sense for the seller to order the survey. Then they could bump up their price by the cost ...

9 years ago
Reply
RE: CHC i80 vs Topcon Hiper V vs Others

Well here is location of not so good to my blind expectationswith all this something should happenits super simple install )&*^)*!&%#^)!*% ne...

9 years ago
Reply
RE: CHC i80 vs Topcon Hiper V vs Others

Topcon $6000.00 plus compounded interest 12 months 3.5% all inall will be good.

9 years ago
Reply
RE: CHC i80 vs Topcon Hiper V vs Others

Hi LeeOn a 200 million dollar site to indicate the scope of the projectthat was going to run 5 years.I had a toe hold on this project and went out to ...

9 years ago
Reply
RE: CHC i80 vs Topcon Hiper V vs Others

Yea topcon sokkia cost me a ton of money and delay a project by 2 weeks and ruined my reputationyes i have a axe to grindhad to call in Leica to put t...

9 years ago
Reply
RE: CHC i80 vs Topcon Hiper V vs Others

Well Im not brand specificbut topcon / sokkia support here is zeroDrop and runAll topcon will see now is my dust

9 years ago
Reply
RE: CHC i80 vs Topcon Hiper V vs Others

I would avoid topcon = garbageYes there maybe more machine operators who know topcon control MC2i guess this is alright if the construction company is...

9 years ago
Reply
RE: Initialising at the base

On new site doing the here and then localizeUsing a Leica GS 14 and Carlson Surv Ce 5.02on new site i would enter 0.000 for the position of the base h...

9 years ago
Reply
RE: Initialising at the base

The Base is a Base ...................... is a Base ...................... is a Base $(!@#$%(!^Turn it offthe next dayturn it onmag mount downI suppos...

9 years ago
Reply
RE: Autodesk strikes again

twdotson, post: 445515, member: 8059 wrote: One of the problems is the race to ridiculous (resolutions) on the part of display makers and the use of 4...

9 years ago
Reply
RE: Initialising at the base

Well if i understand this right In carlson Surve Ce i can switch between projects/jobs on the same site in about 5 secondsIn fact i create jobs someti...

9 years ago
Reply
RE: Estwing vs. Fiskars

paden cash, post: 444879, member: 20 wrote: Only if they're brand-spanking new. Blackberry thickets make short work of old comfy Carhartts down here....

9 years ago