I must really be rusty with the OPUS processing in TBC.
I have a few .dc files that were done with a "Here" position as well as companion Static files that were collect at the same time and sent to OPUS for solutions. I want the "Here" coordinates to match the OPUS derived coordinates and all associated RTK vectors and points to reflect the same.
I thought I used to do this with the "Merge" function, but that process moves the OPUS coordinates to the RTK coordinates.
I even got so desperate that I went to the TBC help videos...............
Any advice and tips would be greatly appreciated.
Bump TTT
You have to set the OPUS point to control prior to merging. Keep in mind my brain is really rusty with yellow brand. I here they aren't even yellow any more..
thebionicman, post: 335737, member: 8136 wrote: You have to set the OPUS point to control prior to merging. Keep in mind my brain is really rusty with yellow brand. I here they aren't even yellow any more..
You're absolutely right TBM. I had the crew run static 4 times over 4 days because I was getting really noisey data and two of the days were thrown out. I was scratching my head and jellied my brain over the last couple of days on re-working the data. Anyway, "the boss" walks into my office, see's the perplexed look on my face and after my very short comment says "did you set the OPUS solution to Control Quality?" Duh..........
All is well now and after talking to our fine local Trimble Rep, the critical part is that the OPUS file needs to be at a higher quality than the "Here" position. I.E Mapping over Survey quality.