Hi, i am a civil engineer student doing my Final year project on Point positioning. During my observation I used GMS 2 pro which is very old device provided by my university, the problem i am facing that the university didn??t update the device after the 6 April 2019 gps rollover so all my observation RINEX data files are showing that the date is 14/12/2000
I tried to edit the date manually but i get error in Topcon tools not enough data or no satellite for my points
Is there any way to edit the date without getting those errors ?
I tried TEQC but I couldn??t know the command that change the date I started to believe it is not for editing the date. For all The professionals here please guide me , thanks
Try the TEQC option -week, providing the correct week number for your session.
@bill93 i tried this?ÿ
teqc -week 2113 inputfile.00O > output.00O
it doesn??t change it just make a copy of the original file
i tried editing the original tps file i get this message
'first point.tps': wrong GPS week of 2113? GPS NAV ToW minus observation epoch = 504 hours
(acceptable difference between data epoch and ephemeris week+ToW is set at +/-12.0 hours)
my observation was on 7/7/2020
'first point.tps': wrong GPS week of 2113? GPS NAV ToW minus observation epoch = 504 hours
(acceptable difference between data epoch and ephemeris week+ToW is set at +/-12.0 hours)
this is for the first point?ÿ
for the second point when i change the week it either set it to 10/7/2020 i put week 2113 but for some reason it changes the day is there any solution for both problems ?
Search the forum for rinexdate.?ÿ It may do what you're looking for.
https://sgss.ca/tools/rinex_date.html
Wrote that utility for this situation some time ago, free to use of course.