I had this one job where I was checking the slope on a pipe with the level and I noticed the slope was off. So I checked my notes in the book and everything looked good. Then I picked up the level and set up again, re-shot the BM, checked the slope on the pipe again, then checked my notes again. I had the exact same results as before. Brought it to the contractors attention and he said the laser level said it was good. Showed him my notes and he still wouldn’t believe me. Set up his laser level and checked it and he said it was fine. So I said ok and moved on to the other job on the site. Couple days later was on site, I noticed the pipe had some more bedding under it. So I set up and checked it again and it was dead on where it should be. Guess he figured out what was going on and fixed it. He was pretty adamant about it though. Lol
Anyone else got any good stories about disagreements with contractors on the job site?