Activity
 
Notifications
Clear all
Matochen
@matochen
Registered
Joined: February 23, 2015 3:28 am
Topics: 1 / Replies: 4
Reply
RE: No control data - TS1200/15

> Matochen what I am getting from your post is all anyone is concerned about is the day to day changes in the track so the ability consistently tie...

10 years ago
Reply
RE: No control data - TS1200/15

> > So we're setting up track monitoring targets 30m either side of the UTX in 5m increments, shooting a baseline survey then monitoring them po...

10 years ago
Reply
RE: No control data - TS1200/15

I believe I can only use a resection If I know the coordinates of the control points (which I unfortunately do not)Thank you for posting though.

10 years ago
Reply
RE: No control data - TS1200/15

> > Hi,> > > > I am about to start 6 weeks of track monitoring for UTX works across South east England railways. I am an assistant w...

10 years ago
Topic
Replies: 17
Views: 6