 jpb
(@jpb)
Posts: 88
Trusted Member Registered
 

Yes, once I find a new place of employment a formal complaint will be filed with the board right before I turn in my resignation letter. 

 
Posted : 23/07/2020 6:48 am
(@tim-v-pls)
Posts: 404
Reputable Member Registered
 

@jitterboogie would you mind putting "ILC" and "ISP" in an abbreviation table?

 
Posted : 23/07/2020 9:31 am
(@thebionicman)
Posts: 4437
Famed Member Customer
 

@lukenz

Many of our States are seeing rulings equating the existence of a fence to a boundary agreement. A professional explains these things to potential clients. Others simply join the race to the bottom...

 
Posted : 23/07/2020 10:19 am
(@jitterboogie)
Posts: 4275
Famed Member Customer
 

@tim-v-pls

Sure thing: 

ILC  Improvement Location Certificate  good money maker, only allow to be created by a survey, not a survey so kinda meh. Realtors love them.

ISP Improvement Survey Plat A real survey plat with elevations and can be used to build and design with. Realtors hate these, because its real.

 

My opine is just that though, from my personal experience.

 
Posted : 23/07/2020 10:22 am
(@charles-l-dowdell)
Posts: 817
 

Approximate today, actual corner tomorrow because a surveyor set it.

 
Posted : 23/07/2020 10:28 am
(@tim-v-pls)
Posts: 404
Reputable Member Registered
 

@jitterboogie

Thank you. The descriptions are similar to what I presumed from the context but the abbreviations aren't something I'm familiar with.

 
Posted : 23/07/2020 11:11 am
(@lukenz)
Posts: 513
Honorable Member Registered
 

@thebionicman

Yes our adverse possession legislation is much, much harder to prove than comments in this thread indicate is the case in US.  Mistaken marking of a boundary (i.e by Dodgey Surveyors R Us) is specifically excluded as grounds, court will go back to last recorded plan of boundaries.

 
Posted : 23/07/2020 11:14 am
(@dmyhill)
Posts: 3082
Famed Member Registered
 

@jpb

That is not a fun situation.

 
Posted : 23/07/2020 12:05 pm
(@mightymoe)
Posts: 9920
Illustrious Member Registered
 

@paden-cash

Or you stake the ROW and flag the existing ROW for which the utility line needs to be either inside the ROW for some jobs and outside for others and the construction crew uses the staked line for centerline, wiping out the monuments and putting half the utility line outside the easement. 

 
Posted : 23/07/2020 12:16 pm
(@dmyhill)
Posts: 3082
Famed Member Registered
 

@paden-cash

 

In WA the courts have decided that physical monuments by the original surveyor hold over the recorded plat. There are many that observe that such a situation (and other case law) could create a conflict with the Statue of Frauds.

 

    MARTIN OLSON et ux., Respondents,
                               vs.
                    CITY OF SEATTLE, Appellant

                          No. 4419
                SUPREME COURT OF WASHINGTON
                     30 Wash. 687, 71 P. 201
                    January 10, 1903, Decided

 
Posted : 23/07/2020 12:20 pm
(@dmyhill)
Posts: 3082
Famed Member Registered
 

@dave-lindell

 

Well, I dont know what he meant, but in practice, I have done the same a few thousands of times. Set a hub and lath at the corner of the plat, and then set "actual" corners (meaning rebar and cap per the law) when the grading and utility install is finished.

They even used to let you do that before the plat was recorded, you just installed the "actual" monuments after the improvements. The Great Recession revealed that you must set centerline and corner monuments before recording, or you might never see them. There are whole plats with zero monuments set from that era. 

 
Posted : 23/07/2020 12:28 pm
(@dmyhill)
Posts: 3082
Famed Member Registered
 

@lukenz

Posted by: @lukenz

No one wants to pay as much a fence costs just to know if it's in the right place.

Why not? Around here a fence builder is a dude with a truck and a saw. Zero barrier to entry. How is it possible that a fence builder can go in and do a day's work and make more than a surveyor on the same line. 

If that is the case, I am building fences!

 
Posted : 23/07/2020 12:31 pm
(@tim-v-pls)
Posts: 404
Reputable Member Registered
 

edited ... political...

 
Posted : 23/07/2020 1:37 pm
(@lukenz)
Posts: 513
Honorable Member Registered
 

@dmyhill

Easy, materials are 2k plus labour if you don't build it yourself for single side residential section, staking survey is 1-1.5k, recorded legal pegs, add 1k. Hence legal pegs more than fence

 
Posted : 23/07/2020 4:54 pm
(@holy-cow)
Posts: 25292
 

You bet the cost of the fence can easily be far more than the cost of the survey, but tearing it back out and moving it following a real survey is priceless..................to the adjoiner who now hates you.

 
Posted : 23/07/2020 7:19 pm
Page 3 / 4